article 6 technical documents

6.1 party b shall, according to the delivery schedule and details stpulated in

appendix 2to the contract, deliver the documents at________________.

6.2 the date stamped by the air transportation ageney at____________,shll be taken

as the actual date of delivery paryt a shall send to party b a photostat copy of the

airconsignment note shwing the stampde date of arrival. 

6.3 within twenty-four hours after the despatch of each lot of the technical documente,

party b shal1 notify party a by cable or telex of the contract number, number and date

of the air consignment note, items of the documents, number of pieces, airmail to

party a two copies of each of the air consignment note and detaikled list of the

technical documents.

6.4 if the technical documents are foumd lost, damaged or mutilated during air

trans-portation, party b shall supply party a free of charge with a second lot of

documents within thechortest possible time but not later than thirty days after it has

received from party a the writtennotice. within sixty days after party a has received

the documents from party b,if party a does not declare the shortage and request to

cover the same, it is considered asa-cepted.

6.5 the technical documents shall be in english and based on metric system of

measure-ments.

article 7 verification and acceptance

7.1 the verification test on the first samplemachine of the contracted product shall