國際專利許可契約(附英文)

by forcer majeure events such as war, serious flood, fire, typhoon and earthquake,

or other events agreed upon between both parties, the term for the execution of the

contract may be extenede by a period equal to that affected by the event(s).

13.2 the involred party shall notify the other party by telex or cable within the

shortest possible time of the occurrence of the force majeure event and within l4 days

thereaftersend by registered airmail to the other party a certificate issued by the

relevant competent authori- ties for confirmation by theother party.

13.3 should the force majeure event last more than one hundred and twenty(120)con-

secutive days,both, parties shall settle the question of further exccution of the

contract through friendly negotiations as soonas possible.

article l4 arbitration

14.1 all disputes arisint from the execution of or in connection with the cotract

shallbesettled through fricndly consultations between both parties. in case no settlement

can be reached through consultations, then the disputes shall be submitted to

arbitration.

14.2 the arbitration shall take place in stockholm, sweden, and be conducted by

thearbitration tribunal of thestockholm chamber of commerce in accordance with the

statutes of the said tribunal.

14.3 the arbitration award shall be final and binding upon both parties.

l4.4 the arbitiation fee shall be borne by the losing party.

l4.5 if the arbitration involves only a part of the contract, then in the course of