develop-ment of or improvement on the contracted product.
9.2 party b guarantees that the technical documents to be supplied by party b are
com-plete,correct,legible and are to be despatched in time.
9.3 if the documents suppied by party b are not in conformity with the stipulation
in article 6, party b shall, within the shortext possible time but not later than 3o
days after re-ceipt of party a’s written notice, despatch free of charge to party a
the missing or the cor- rcet and legible technical socuments.
9.4 if party b fails to despatch the said documents within the stipulated period as
per appendix 2 party b shall pay penalty to party a in the following proportions:
(a)...percent of the total contract price for delay from 1 to 4 weeks.
(b)...percent of the total contract price for delay form 5 to 8 weeks.
(c)...percent of the total contract price for delay exceeding weeks;
9.5 the payment of penalties by party b to party a as stipulated in article 9 shll
not releve party b of its obligation to deliver the said documents.
9.6 whenever the delay in delivering the said documents exceeds 6 months, party a
shall be entitled to terminate the contract at its discretion and party b shall be
obliged to re- fund party a all its payments together with the corresponding ingerest
at the rate of... per-cent per annum.
9.7 if the verification tests fail with the responsibility lying with party b and