此時,業主可在書面通知承包人_______天后進駐工地,並將承包人逐出,由此不會造成契約無效,或解除承包人的任何契約義務或責任,或影響契約賦予業主或工程師的權利和權力,業主可自己完成工程或另雇其他承包人完成工程。為完成工程,業主和其他承包人可充分使用其認為合適的,按本契約規定被視為是專門為施工而保留的建築設備、臨建工程和材料,業主可隨時出售上述任何建築設備、臨建工程和未使用的材料,並將出售收人抵付按契約規定承包人應支付或可能支付給他的任何款項。 

(2)the engineer shall,as soon as may be practicable after any such entry and expulsion by the employer,fix and determine ex parte,or by or after reference to the parties,or after such investigation or inquiries as he may think fit to make or institute,and shall certify what amount, if any,had at the time of such entry and expulsion been reasonably earned by or would reasonably accrue to the contractor in respect of work then actually done by him under the contract and the value of any of the said unused or partially used materials,any constructional plant and any temporary works.

63.2業主進駐工地並逐走承包人之後,工程師應儘快單方面,或通過了解雙方當事人,或在作過他所認為恰當的調查或諮詢之後作出安排或決定,並證明到此種進駐與被逐時為止,按事實上已完成的契約工程,承包人已獲得或理應獲得的款項(如果有),以及計算出上述任何未使用或只部分使用的材料、建築設備和臨建工程的價值。

(3)if the employer shall enter and expel the contractor under this clause,he shall not be liable to pay to the contractor any money on account of the contract until the expiration of the period of maintenance and thereafter until the costs of execution and maintenance,damages for delay in completion, if any,and all other expenses incurred by the employer have been ascertained and the amount thereof certified by the engineer.the contractor shall then be entitled to receive only such sum or sums,if any,as the engineer may certify would have been payable to him upon due completion by him after deducting the said amount.if such amount shall exceed the sum which would have been payable to the contractor on due completion by him,then the contractor shall,upon demand,pay to the employer the amount of such excess and it shall be deemed a debt due by the contractor to the employer and shall be recoverable accordingly.

63.3如果業主按本條規定進駐工地並逐走承包人,他應在維修期滿,且所有施工和維修費、延誤完工賠償費(如果有)、和業主所發生的其他費用被核實,且經工程師證明後,方才負責對承包人按契約進行支付。此時,承包人有權得到的款額(如果有)僅為工程師證明,因他妥善完工而應得的款額減去上述款項之差。如上述費用超過承包人妥善完工應得的款額,經要求,承包人得向業主支付此超出部分款額,超出部分應視為承包人對業主的負債,且可照此收回。